UCSB DFSS Contracting Services
Back to list

RecCen Aquatics Complex Renewal

Posted 4/23/2007

Notes

The consultant selected for the RecCen Aquatics Complex Renewal project will provide the campus with design & construction administration services for renewal of the 1995 Aquatics Complex. Estimated construction cost is $1,250,000. Proposals due May 15, 2007.

Posted 4/24/2007


The Statement of Qualifications Form must be signed by a responsible member of the firm applying for the project and submitted with the proposal.

Posted 4/24/2007


Requests For Proposals have been received and are being evaluated by the University. The short-listed firms will be posted at a later date after the evaluation process has been completed.

Posted 5/23/2007


CONSULTANT SELECTION: Aquatic Design Group

Posted 8/23/2007


Attachments