Hatlen Theater - Lighting, Sound, & Communications/Data Upgrade

Posted 4/02/2010

Notes

Prequalification documents have been received and are under review by the Facility. Prequalification notices will be sent to all respondants.

Posted 4/23/2010


On April 19, 2010 Contractor Prequalification Documents were received from three (3) respondents for this project. The University evaluation committee has had the opportunity to review and evaluate the Statements of Qualifications. None of the respondent firms qualified.

Posted 4/28/2010


The University will re-issue the prequalification documents for this project that will modify the criteria in the documents by Addendum. The University encourages all respondents to re-submit. In addition, another Conference and Job Walk will be offered to allow new respondents to submit their qualifications.

Posted 4/28/2010


Addendum Three changes the Bid Opening date to 5/19/2010 @ 2:30PM

Posted 4/30/2010


Per Addendum Four, Bid Opening Date has been changed to June 2, 2010 at 2:30 PM

Posted 5/20/2010